Blades Building LtdBLADESBUILDING
Rules & process

Foundations for house extensions: types, depths and costs

What determines whether your extension needs strip, trench fill, raft or piled foundations.

Foundation type is decided by ground conditions and what is nearby, not by the size of the extension going on top. Two identical single-storey extensions on the same street can end up with very different foundation designs once trees, drains, made-up ground or a sloping plot are taken into account. Because foundations are entirely invisible once the job is finished, they are also the part of the budget most likely to be underestimated by anyone pricing from a drawing alone. This guide covers the main foundation types, when each is used, and the factors that push a straightforward dig into something more involved.

Strip foundations

A strip foundation is a continuous trench of concrete under the load-bearing walls, wide enough to spread the building's weight into ground of reasonable, consistent bearing capacity. It is the traditional approach for straightforward single-storey extensions on firm, undisturbed ground, and remains the most common foundation type for domestic work where site conditions are unremarkable.

Trench fill foundations

Trench fill is a deeper, narrower trench filled almost to ground level with concrete rather than built up with blockwork. It has become the default choice for most modern domestic extensions because it reduces the amount of time bricklayers spend working below ground and copes better with deeper excavations, which are increasingly common due to tree influence and services.

Raft foundations

A raft foundation is a reinforced concrete slab spanning the whole footprint, spreading load over a wide area rather than concentrating it in trenches. Rafts are used where ground conditions are poor, where deep trench excavation is impractical, or where existing foundations nearby cannot be undermined by a deep dig. They generally need a specific structural design rather than a standard building control detail.

Piled foundations

Where ground conditions are genuinely unsuitable for shallow foundations — soft clay, made-up ground, or proximity to trees with a history of subsidence — piles transfer load down to firmer strata well below the surface, tied together with a reinforced ground beam. Piling is significantly more expensive than trench-based methods but is sometimes the only reliable option, and is common on infill or previously developed plots.

Comparing the options

The table below sets out typical depths, when each type is used, and a broad indicative cost comparison. Ground investigation and, in some cases, an engineer's design are needed before a final choice is confirmed.

Foundation types compared: typical depth, use and indicative cost (UK, 2026)
Foundation typeTypical depthWhen it's usedIndicative cost range
Strip600mm–1mFirm, consistent ground, standard single-storey extension£90–£150 per linear metre
Trench fill1m–2.5m+Standard for most modern extensions, deeper digs, tree influence£110–£190 per linear metre
RaftSlab, minimal depth below groundPoor ground, restricted excavation depth, nearby structures£150–£250+ per m² of footprint
Piled3m–10m+ depending on strataVery poor ground, significant tree influence, made-up ground£250–£500+ per m² of footprint

Figures are broad indicative UK ranges and vary considerably by region, ground conditions and access for plant. A site investigation and, where needed, an engineer's design are required before a firm price can be given.

Trees, NHBC influence distances and building over drains

Trees are one of the most common reasons a foundation ends up deeper or more expensive than expected. NHBC guidance sets influence distances for different species based on their mature height and water demand, and where an extension falls within that distance, foundations typically need to go deeper or be redesigned to avoid future ground movement as roots take up moisture. Building over or near an existing drain run raises its own requirements — Building Regulations (Part H, alongside structural provisions) generally require the drain to be protected with a lintel and bridging over it, or diverted, and building control will want to see this detailed before work starts.

  • High water-demand species (e.g. oak, willow, poplar) have the largest influence distances
  • Removed trees can also affect ground moisture recovery and need separate consideration
  • Drains under or near foundations usually need a designed lintel or diversion, agreed with building control

Why ground investigation matters

A trial pit or borehole, sometimes combined with a desktop study of geological records, tells the designer what is actually in the ground rather than what is assumed. On infill plots or where the history of the site is unclear — old outbuildings, filled ponds, previous industrial use — skipping this step is a common cause of foundation problems discovered mid-dig, which is the most disruptive and expensive time to discover them.

Groundworks in wet weather and over winter

Groundworks are one of the stages most exposed to weather, and a wet spell can turn a straightforward dig into a genuinely difficult one — trench sides can slump in saturated clay, and concrete should not be poured into standing water or onto waterlogged ground without extra preparation. Winter digs also bring a frost risk to freshly poured concrete, which needs protecting if temperatures are forecast to drop before it has cured sufficiently. None of this makes winter groundworks impossible, but it is sensible to build some contingency into the programme and to expect a competent groundworker to pause rather than push on with a pour in genuinely unsuitable conditions, since a foundation poured badly is far more costly to put right later than a few days' delay.

What building control checks at foundation stage

Foundations are one of the notifiable stages building control physically inspects on site, typically once the trench or excavation is open and again once reinforcement (where used) is in place, before concrete is poured. The inspector is checking the depth reached matches what was specified for the ground conditions found, that there is no evidence of soft spots, tree roots or made-up ground that would need the design revisiting, and that any drains or services running through the area have been protected as detailed. Because concrete cannot easily be un-poured, this inspection genuinely needs to happen before the pour, not as a formality afterwards, and a good contractor will build the inspector's visit into the programme rather than treating it as an interruption.

Common questions

Questions we get asked about this

How deep do extension foundations need to be?

There is no fixed figure — depth depends on ground conditions, nearby trees and drains, and building control requirements, and can range from around 600mm on firm ground to several metres where trees or poor ground are involved. A site-specific assessment is the only reliable way to know.

Does a tree near my extension always mean deeper foundations?

Not always, but it is very common. NHBC guidance sets influence distances by species and size, and where the extension falls within that zone, foundations are usually designed deeper or differently to allow for future ground movement.

Can I build over a drain?

Sometimes, provided the drain is protected with a designed lintel and bridging in line with Building Regulations, or diverted around the extension. Building control needs to see and approve the detail before work proceeds.

Why did my foundation quote go up after the site visit?

Foundation costs are notoriously hard to fix from a drawing alone. A site visit and, where needed, trial holes reveal ground conditions, tree influence and services that materially affect depth and design.

Is trench fill always better than strip foundations?

Not necessarily better, but it is often more practical on deeper digs because it reduces time spent bricklaying below ground. The right choice depends on depth required and ground conditions rather than one being universally superior.

Not sure what your ground needs?

We will assess the site, factor in trees and drains, and give you a written quote based on what the ground actually requires.